Sample Compliance Report

Poet Hill Residences

Worcester, MA

Verdict

CONDITIONAL

47

Passed

8

Failed

12

Need Review

67 total checks performed

Jurisdiction: Worcester, MA

IBC 2015IRC 2015IECC 2021IPC 2015IMC 2015NFPA 13NFPA 72780 CMR (MA Amendments)

Critical Issues (3)

1. Missing fire-resistance rating on corridor walls

IBC 1017.2 — Corridor walls on floors 2 and 3 lack required 1-hour fire-resistance rating for Group R-2 occupancy. Must be resolved before permit issuance.

2. Egress width insufficient at Stair B

IBC 1005.1 — Stair B measures 42" clear width; minimum 44" required for occupant load > 50. Structural modification or load recalculation needed.

3. No COMcheck documentation provided

IECC C402.1 — Energy code compliance documentation (COMcheck or equivalent) not included in submission. Required for Climate Zone 5A.

Detailed Findings

Means of Egress

2 passed2 failed1 need review
IBC 1005.1Egress Width — StairwaysFailed

Stair B measures 42 inches clear width. Required minimum is 44 inches for occupant load > 50 per IBC 1005.1. Sheet A3.2 shows stair B serving floors 2-4 with calculated occupant load of 87.

Recommendation

Widen Stair B to minimum 44 inches clear width between handrails, or demonstrate occupant load does not exceed 50 per floor served.

IBC 1017.2Corridor Fire-Resistance RatingFailed

Corridor walls on floors 2 and 3 are not indicated with a fire-resistance rating on sheets A2.1 and A2.2. Required 1-hour rating for Group R-2 occupancy with sprinklers per IBC Table 1020.1.

Recommendation

Add 1-hour fire-resistance rating notation to all corridor walls on sheets A2.1 and A2.2. Provide UL assembly references.

IBC 1010.1.9Door Operations — HardwarePassed

All egress doors shown with lever hardware operable without tight grasping, pinching, or twisting. Panic hardware specified on assembly spaces per A8.1 door schedule.

IBC 1006.3Number of ExitsPassed

Two exits provided per floor for occupant loads between 50 and 500. Verified on sheets A1.1 through A1.4. Exit locations comply with IBC 1007.1 separation requirements.

IBC 1015.2Exit Access Travel DistanceNeeds Review

Travel distances appear compliant at 230 feet maximum (250 feet allowed with sprinklers for Group R), but dimensions are not clearly annotated on A1.3 for the 3rd floor east wing.

Recommendation

Annotate exit access travel distance on sheet A1.3 for the 3rd floor east wing corridor to verify compliance.

Fire Protection

2 passed2 need review
NFPA 13 8.15.1Sprinkler Coverage — ClosetsPassed

Sprinkler heads shown in all closets exceeding 24 sq ft per NFPA 13 requirements. Verified on FP1.1 through FP1.4.

NFPA 72 17.7.1Smoke Alarm PlacementNeeds Review

Smoke alarm locations shown on E2.1-E2.4 but detector spacing in the 3rd floor common corridor exceeds 30 feet. NFPA 72 17.7.3.2.1 limits spacing to 30 feet unless engineering analysis provided.

Recommendation

Add smoke detector in 3rd floor corridor between units 305 and 309, or provide ceiling height adjustment calculation per NFPA 72 17.7.3.2.3.

IBC 903.2.8Automatic Sprinkler System — Group RPassed

NFPA 13 automatic sprinkler system specified throughout per IBC 903.2.8 for Group R-2 occupancy. Hydraulic calculations referenced on sheet FP0.1.

IBC 704.3Exterior Wall Fire-ResistanceNeeds Review

South elevation exterior wall is 8 feet from property line per site plan. Fire-resistance rating requirement depends on openings percentage. Opening area calculations not provided.

Recommendation

Provide exterior wall opening area calculation for the south elevation per IBC Table 705.8. Include fire-resistance rating if openings exceed allowable percentage.

Energy Conservation

1 passed1 failed1 need review
IECC C402.1Building Thermal Envelope — COMcheckFailed

No COMcheck documentation or equivalent energy compliance documentation found in the drawing set. IECC C401.2 requires documentation demonstrating compliance with prescriptive, total building performance, or energy rating index requirements.

Recommendation

Submit COMcheck report or equivalent energy code compliance documentation demonstrating the building envelope meets IECC 2021 requirements for Climate Zone 5A (Worcester, MA).

IECC C402.2Roof InsulationPassed

Roof assembly detail on sheet A5.3 specifies R-30 continuous insulation above deck, meeting IECC Table C402.1.3 minimum of R-25ci for Climate Zone 5A.

IECC C402.4Fenestration — U-factorNeeds Review

Window schedule on A8.2 specifies U-0.32 for all windows. IECC Table C402.4 requires U-0.36 max for Climate Zone 5A. Values comply, but no NFRC certification labels referenced.

Recommendation

Add NFRC certification label references to the window schedule on sheet A8.2 to document rated U-factor values.

Structural

3 passed
IBC 1607.1Live Load — CorridorsPassed

Structural plans specify 100 psf corridor live load per IBC Table 1607.1 for Group R-2 corridors above first floor. Load path shown on S2.1 through S2.4.

IBC 1609.1.1Wind Load ParametersPassed

Wind load design parameters noted on S0.1: Risk Category II, Ultimate Wind Speed 120 mph, Exposure B. Consistent with ASCE 7-16 for Worcester, MA.

IBC 1613.1Seismic Design ParametersPassed

Seismic design criteria on S0.1: SDS = 0.154, SD1 = 0.068, Seismic Design Category B. Values match USGS data for the site coordinates.

Accessibility

2 passed1 need review
IBC 1104.1Accessible RoutePassed

Accessible route provided from public way to all dwelling units and common spaces. Elevator serves all floors per sheet A4.1. Ground floor at grade entry confirmed on A1.1.

IBC 1107.6.2.1Type A & B Dwelling UnitsNeeds Review

Unit plans show 2% Type A units and all ground floor as Type B. Need to verify unit count to confirm 2% of total meets minimum of 1 Type A unit.

Recommendation

Annotate total unit count and Type A/Type B designation on the code summary sheet to verify compliance with IBC 1107.6.2.

ADA 604.5Grab Bars — Common Area RestroomsPassed

Grab bars shown at accessible water closets in lobby restrooms per ADA 604.5. Side wall grab bar 42 inches, rear grab bar 36 inches. Mounting heights at 33-36 inches AFF.

Plumbing

1 passed1 need review
IPC 403.1Minimum Plumbing FixturesPassed

Fixture count per IPC Table 403.1 for Group R-2: minimum water closets, lavatories, and bathtub/showers provided for each dwelling unit. Common area restrooms provided in lobby.

IPC 607.1Hot Water Supply TemperatureNeeds Review

Domestic hot water system shown on P1.1 with central boiler. Anti-scald provisions not specified on drawings.

Recommendation

Add thermostatic mixing valve specification and maximum delivery temperature notation (120F max) on plumbing riser diagram per IPC 607.1.